Answer the questions based on the following information. Mulayam Software Co., before selling a package to its clients, follows the given schedule.The number of people employed in each month is:Due to overrun in ‘design’, the design stage took 3 months, i.e. months 3, 4 and 5. The number of people working on design in the fifth month was 5. Calculate the percentage change in the cost incurred in the fifth month. (Due to improvement in ‘coding’ technique, this stage was completed in months 6-8 only.)
Write Comment
Comments
By: anil on 05 May 2019 02.33 am
In given table, value of cost for 5th month = $$(N) imes (C)$$ (No.of employer for 5th month = N and cost per person for 5th month = C)
So value of cost for 5th month before overrun = $$4 imes 10 = 40$$
value of cost for 5th month after overrun = $$ 5 imes 20 = 100 $$
Change = 60
%change = $$frac{60}{40} imes 100$$ = 150
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use
So value of cost for 5th month before overrun = $$4 imes 10 = 40$$
value of cost for 5th month after overrun = $$ 5 imes 20 = 100 $$
Change = 60
%change = $$frac{60}{40} imes 100$$ = 150