1.
Direction: Study the given graph carefully to answer the questions that follow Number of days taken by three carpenters to finish making one piece each of four different items of furnitureIf Carpenters X, Y and Z were to make a table together how many days would they take ?
Write Comment
Comments
By: anil on 05 May 2019 01.31 am
Individually, they take 2, 3 and 6 days respectively to make the table. So, their combined one day work = 1/2 + 1/3 + 1/6 = 1 So, the three of them can finish making a table in 1 day.