1. 50 men can complete a work in 28 days. They started the work together, but at the end of each $$10^{th}$$ day, 10 men left the job. The work was completed in how many days?
Write Comment
Comments
By: anil on 05 May 2019 02.08 am
Let a man can do 1 unit/day => Total work = $$50 imes28=1400$$ man days So, work done in first 10 days by 50 men = $$10 imes50=500$$ man days Then, work done in next 10 days by 40 men = $$10 imes40=400$$ man days Similarly, 300 man days after next 10 days and 200 after that. Thus, $$500+400+300+200=1400$$ man days => Total days required = 40 days => Ans - (C)