1. 30 women do half of the total work in 30 days. How many more women will be required to complete the remaining work in 10 days?
Write Comment
Comments
By: anil on 05 May 2019 02.05 am
30 women do half of the total work in 30 days Let $$x$$ women are required to complete the remaining half work. Using, $$M_1D_1=M_2D_2$$ => $$30 imes30=x imes10$$ => $$x=frac{900}{10}=90$$ $$ herefore$$ Number of more women required = $$90-30=60$$ => Ans - (C)